ElbX Tunnel | A breakthrough for Germany’s energy transition

|   Projects

The successful breakthrough of the ElbX tunnel marked an important milestone in the SüdLink project and for the energy transition in Germany.

After tunnelling for around 5.2 kilometres, the tunnel-boring machine reached the target shaft, thereby linking Schleswig-Holstein and Lower Saxony beneath the River Elbe. The project is one of the key components of Germany’s energy infrastructure and will make an important contribution to a secure electricity supply in future.

Key project for the energy infrastructure

The ElbX Tunnel forms part of the SüdLink project, Germany’s largest electricity transmission scheme. From 2028, six high-voltage direct current (HVDC) cables will run through the tunnel, transporting electricity generated from renewable sources from northern to southern Germany. This will fulfil a key prerequisite for the implementation of the energy transition and the expansion of an efficient energy infrastructure.

Integrated engineering services from iC

iC supported the project with a range of interdisciplinary services. These included planning permission, detailed design, infrastructure and structural engineering, geotechnical design and BIM-based 3D modelling. Close collaboration between the various specialist departments ensured the successful delivery of this complex infrastructure project.

Tunnelling is progressing faster than planned

Construction progress was positive: thanks to improved ground conditions over the final 400 metres, the tunnel breakthrough was achieved ahead of schedule. As a result, a peak tunnelling rate of up to 32.6 metres per day was achieved over the final metres.

The successful completion of this phase of construction marks another important step towards a sustainable and future-proof energy supply in Germany.