Flood protection on the Isel River in Lienz | Final phase until May 2026

|   Projects

After three winters of intensive work during low water periods, the flood protection project on the Isel River in Lienz is nearing completion. In addition to increasing safety, new recreational areas are being created along the river and ecological compensation measures are being implemented.

The glacier-fed Isel River poses particular challenges for Lienz due to its dynamic nature and seasonal water flow. After three winters of carefully planned construction work, the flood protection project is now entering its final phase. Despite exceptionally difficult winter conditions on site, the work remains fully on schedule.

Implementation over three construction winters – progress despite difficult conditions

The work was carried out over three winters, specifically during periods of low water. Even challenging weather conditions and particularly cold spells did not slow down the progress of the project: the measures are still fully on schedule and are now in their final phase.

Planning and local construction supervision by flussbau iC

flussbau iC is responsible for planning and local construction supervision and supports implementation with a focus on safe execution, quality control, and coordination. This ensures consistent control over the implementation of protective measures and accompanying design elements.

Bridge and new riverbank areas by May 2026

The new Isel pedestrian bridge is scheduled to open by the end of April. The “Sonnenlounge” riverside promenade and a recreation area near the Schlossbrücke bridge will follow in May. In addition, the pedestrian areas on both banks will be redesigned and the paths along the Isel will be significantly improved.

Ecological compensation measure with side channel

In addition to the flood protection measures, a new side channel was created near the castle bridge. This measure serves to enhance the ecological value of the water area and creates additional habitats.